Renovation support

Heat pump subsidy in canton Neuchâtel

In Neuchâtel, the Buildings Programme supports an air/water, ground/water or water/water heat pump that replaces oil, gas or fixed electric heating, up to 70 kW. The amount follows the thermal output, capped at 50 W per m² of heated floor area. The application goes by post, before works begin. General conditions 2026, as of 1 September 2026.

There is no building-age condition for the heat pump: the building's first official valuation only needs to be at least two years old. Support is capped at 50% of the investment.

Covered rates and scope

Indicative official rate. The final amount depends on the application and cantonal decision.

Who can apply

  • Any owner of a building in Neuchâtel: individual, company, municipality. Support is paid to the owner; the canton and the Confederation are excluded.
  • An existing building whose first official valuation is at least two years old.
  • Replacing an oil, gas or fixed electric resistance heating system.
  • A manually fed wood heating replaced by a heat pump goes through a special measure (NE20), with its own form, also before works.

What is not subsidised

  • Replacing an existing heat pump: it is not among the eligible heating systems, and an installation already subsidised is not subsidised twice.
  • Works started before the application is received by post.
  • New buildings: the legal requirements for new buildings are not subsidised.
  • A project already registered with another CO2 compensation programme.

Technical conditions

  1. Heat pump with an electric motor, 70 kW thermal at most, used as the main heating system.
  2. Air/water heat pump: provide a CECB whose envelope rating is class A, B, C, D or E (not required for SIA categories VII to XII).
  3. No oil or gas backup: a bivalent fossil installation makes the project ineligible; a renewable backup remains allowed.
  4. Up to 15 kW thermal: the heat pump system-module standard, with an installation certificate at completion; above that: an EHPA or national quality label and the SwissEnergy performance guarantee.
  5. Geothermal probes: a drilling company holding a quality certificate recognised in Switzerland; works declared through the Guichet unique (GAPE application).
  6. Subsidised output capped at 50 W thermal per m² of energy reference area before works.

The application, step by step

  1. Choose your route: the heat pump belongs to the individual measures, alongside per-element insulation; in the same project it cannot be combined with renovation by CECB classes or with Minergie.
  2. For an air/water heat pump, have the CECB drawn up; ask the installer for a quote with the system-module confirmation or the performance guarantee.
  3. Enter the project on the Buildings Programme portal (Neuchâtel), then post the signed form and its attachments: the application only counts once received.
  4. After the acknowledgement of receipt, works may start at your own risk if the project is authorised; the grant decision arrives by post.
  5. Report completion no later than 24 months after the decision, with the completion statement sent by post; the energy service (SENE) checks, then pays.

Check the building by address

Check the building by address

The address identifies the canton and prepares an initial view of plausible support.

Submit the application and wait for the decision required by the programme before starting work or making a binding commitment.

Frequently asked questions

Does my electric heating have to be replaced in Neuchâtel?

Yes: the cantonal energy act bans fixed electric resistance heating from 1 January 2030 (art. 54 LCEn). In homes, central water heaters running on electricity alone must also be replaced or supplemented by then (art. 55).

Is a CECB needed for heat pump support in Neuchâtel?

For an air/water heat pump, yes: a CECB with an envelope rating of class A to E must be provided. The general conditions do not require one for a ground/water or water/water heat pump.

My house has no water radiators: is there support in Neuchâtel?

Yes, measure IP19 helps install water-based heat distribution when decentralised electric, oil or gas heaters are replaced. It can be combined with the heat pump, but needs its own application, also before works.

Can I keep my oil boiler as a backup?

No: in Neuchâtel, a bivalent installation with fossil energy makes the whole project ineligible. A renewable backup, such as solar thermal or wood, remains allowed.

Can I combine a heat pump and insulation in Neuchâtel?

Yes: both are individual measures, which can be combined. They cannot, however, be combined with renovation by CECB classes or Minergie in the same project, and the route cannot be changed midway.

What does the law require when replacing an oil boiler in Neuchâtel?

In an existing home, non-renewable energy may cover no more than 80% of heat demand after the replacement; fully renewable heating is required where technically possible at no extra cost (art. 53 LCEn).

Is the “heat renewably” advice paid for?

No: this on-site advice from an approved expert is free for the owner and funded by the Confederation. It helps choose the system before asking for quotes.

Official sources and date

retrieved on 2026-11-25